Viscount Bennett Update

12 hours ago
1 min read

The developer of the former Viscount Bennett site has shared an update on the project with the community association.



Where the project stands


  • The current concept is seven six-storey buildings with one level of underground parking.

  • The master plan is preliminary. It is subject to City approvals and market conditions, and may change as the project progresses.

  • The developer is awaiting approval of the construction drawings before moving forward with the permitting process.

  • Construction was originally expected to begin in November 2026. Because of the approval process, the start may be delayed to February 2027.

  • The developer is targeting completion of the final building by December 2033, subject to receiving the required approvals and proceeding without appeals or other unforeseen delays.


Have a question about the project? Send us your questions by email and we will share them with the developer.


This information and the associated rendering are being provided for community information purposes only. They are not to be shared, distributed, reproduced, or replicated without the prior consent of ownership.