17th Ave West Main Streets Update

This just in from the City of Calgary:


Work completed on west 17 Avenue

This season crews were working on the north side of 17 Avenue between 37 and 33 Streets, and on the south side between 33 and 30 Streets SW. Work included new sidewalks, street lights, wheel chair ramps, a multi-use pathway on the north side of 17 Avenue, and improved pedestrian crossings.


Want to take a walk-through of the finished product, you can check it out here.


Work we will finish this season

  • Traffic signal at 17 Avenue and 35 Street SW

  • New street light installation

Work we will complete in 2021

  • Upgrading the water main and sanitary utilities along 17 Avenue between 26 and 29 Streets SW and along 26 Street between Bow Trail and 17 Avenue SW

  • Pedestrian realm improvements between 24 and 37 Streets SW

  • Pedestrian realm improvements and lifecycle work on the 17 Avenue bridge over Crowchild Trail

Winter 2020

  • Over the winter, crews will continue to work on traffic signal improvements along

  • 17 Avenue SW, including 29 Street, 27 Street, 26 Street, and 25 Street SW

  • Sidewalks and the multi-use pathway will be open for use